SUPERVISION ng the Wall in The Plant Primary Crushing the Cerro Corona Project (Minera Goldfields Peru SA) located in the district Hualgayoc, Hualgayoc Province, Cajamarca
Construction of a copper concentrator plant with a capacity 17,000 t/day, which included civil works, structural fabrication and assembly, equipment assembly, fabrication and assembly of 21 tanks, pipelines installation up to mechanical completion.
Scope included the erection of one ball mill and one ball mill with a 6.1 m diameter and one SAG mill with a 7.3 m diameter.
Source: GyM
17000Output Tonnes per day1850Engineering man hours (K)20.01Ball Mill diameter (ft)16500Concrete poured (m3)3700Equipment assembly (Tonnes)2100Structural assembly (Tonnes)23.95SAG Mill diameter (ft)1Number of SAG Mill installed 1Number of Ball Mill installed