Ollachea gold project

Ollachea gold project

Milestones

  • 2014

    Approved for construction

  • 2013

    Environment Impact Assessment (EIA) Approved

Confidential
2014
US$ 108K

Feasibility studies

Confidential

Mining Plus
2014
US$ 35.9K

Technical report

Mining Plus

Technologia XXI
2013
US$ 160.7K
Coffey International Ltd
2012
US$ 108K

Feasibility studies

Coffey International Ltd

JJC Contratistas Generales S.A. (JJC)
2011

Tunnel construction

JJC Contratistas Generales S.A. (JJC)

1.2Length (km)

Hydrogeological studies

Geoservice Ingeniería

AMEC plc
US$ 108K

Detailed engineering

Anddes Asociados

Feasibility design of tailings pond access. Detailed engineering of the bridge over the creek Cuncurchaca. Study options of crossing the creek.

Detailed engineering of tailing depositing, dump dumps, excess material dumps, topsoil dumps. Field investigations, geotechnical analysis, hydrology and civil design are included.

Source: Anddes Asociados

More contracts, contractors and photos are included in the PDF.

Snapshot

Capital Expenditure
US$ 177.5M
Project Status
Construction & Development
Production starting date
March 2016
Construction Started
June 2014
Gold Annual Output (Ounces)
113000

Top Contractors

Geoservice Ingeniería
Technologia XXI
Anddes Asociados
Coffey International Ltd
AMEC plc