GMI developed the Detailed Engineering of the Sulfuric Acid Plant for the Copper Circuit. The design of the Gas Cleaning process was carried out by Fleck Chemical Industries Inc. (FCII) and the design of the producing sulfuric acid process was carried out by Aker Kvarner Chemetics (AKC). GMI completed the engineering work for this project in July 2009.
Additionally, DRP hired GMI to perform Material and Equipment Management Services for all their PAMA and Modernization projects. These services started in April 2007 and were successfully completed in December 2008.
Source: GMI S.A. Ingenieros Consultores
For this Project Doe Run Peru (DRP) hired the Services of the Canadian Company Fleck Chemical Industries Inc. (FCII), which was responsible for the Basic Engineering of the Lead Circuit Acid Plant and the Design and Selection of Process Equipment.
GMI was responsible for the Detailed Engineering Work Services Outside the Contract Limits of the DRP and FCII contract. This included Preliminary Engineering Works and Auxiliary Systems.
The Sulfuric Acid Plant for Lead Circuit began Operations in late September 2008.